    Written Scheme of Examination: what a good PSSR WSE actually contains

    HSE ACoP L122 update reminds duty holders that a WSE without pressure/volume calculations, hazard category, and named competent person is not compliant.

    PSSR 2000 · HSE ACoP L122Official text

    The six mandatory elements

    1) A description of the plant and its safe operating limits; 2) the identity of the competent person; 3) the parts of the system to be examined; 4) the nature of the examination (external, internal, functional); 5) the frequency of examination; 6) any preparatory work required. A WSE missing any of these six is defective, and the plant should not be operating on it.

    How Cloud VGP structures the WSE

    Every pressure asset in Cloud VGP carries a WSE record with the six elements above, versioned and signed by the competent person. The engineer running the next thorough examination is prompted with the WSE preparatory work and cannot close the inspection without linking to the WSE version in force.

    Immediate action plan

    • 1Audit each WSE against the six ACoP L122 elements.
    • 2Re-issue any WSE older than 5 years or where the plant has changed materially.
    • 3Store WSEs and Reports of Examination in a single digital register — retain for the life of the plant.
    PSSR WSE
    Written Scheme of Examination
    pressure systems UK
    ACoP L122
    competent person pressure