    COMAH, DSEAR and GMP risk control

    Chemical and pharmaceutical sites in the UK stack a dense regulatory pile: COMAH 2015 (lower and upper tier), DSEAR 2002 (aligned with EU Directives 1999/92/EC and 2014/34/EU as retained), MHRA GMP for pharma, pressure systems under PSSR 2000, cleanroom and utility qualification (WFI, pure steam, compressed air). Cloud VGP centralises every reference.

    Industry challenges

    • DSEAR zoning and equipment suitability
    • COMAH safety case and on/off-site emergency plans
    • Continuous qualification of GMP-critical equipment
    • 21 CFR Part 11 and data integrity

    Regulatory framework

    • COMAH 2015

      Control of Major Accident Hazards Regulations

    • DSEAR 2002

      Dangerous Substances and Explosive Atmospheres Regulations

    • MHRA GMP Annex 1

      Manufacture of sterile medicinal products

    Relevant assets and inspection frequencies

    AssetFrequencyReference
    DSEAR equipment (Zones 0/1/2 & 20/21/22)Every 3 yearsBS EN 60079-17
    Chemical pressure systemsPer WSE (typ. 26 to 120 months)PSSR 2000
    Pressure safety valvesEvery 4 yearsPSSR 2000 / HSG 250
    ISO 5 to ISO 8 cleanroomsEvery 6 to 12 monthsISO 14644-2
    Pharma utilities (PW, WFI, pure steam)Every 12 monthsEuropean Pharmacopoeia
    Air handling units (AHU)Every 12 monthsISO 14644-3
    Toxic gas detectionEvery 6 monthsBS EN 60079-29-2
    Dangerous substance storage tanksEvery 5 yearsCOMAH 2015 / CDOIF

    Digitise compliance for your chemical & pharma

    Centralise your statutory inspections, automate due-date reminders and generate your compliance register in one click. Personalised demo within 24 hours.

    Frequently asked questions — Chemical & Pharma

    Regulatory updates

    The latest obligations, statutory instruments and guidance applicable to this industry.

    All updates